What makes a guarantee "on demand"
A demand guarantee is an undertaking by a bank or other guarantor to pay the beneficiary on presentation of a complying demand, usually without needing to prove that the underlying contract has been breached. Its independence from the underlying contract is what makes it valuable to beneficiaries and risky for applicants. An accessory guarantee or surety bond, by contrast, generally depends on the underlying liability being established. Whether an instrument is one or the other depends on its wording, not its title.
Common types in trade
- Performance guarantees, securing a supplier's or contractor's performance
- Advance-payment guarantees, securing repayment of an advance if the supplier does not perform
- Payment guarantees, securing a buyer's payment obligation
- Retention guarantees, released in place of cash retentions
- Bid or tender guarantees, supporting a tender
Rules and law
Many demand guarantees incorporate the ICC Uniform Rules for Demand Guarantees (URDG 758). Standby letters of credit often incorporate ISP98 or UCP 600. Where rules are incorporated, they govern matters such as the form of demand and the examination period. The governing law of the guarantee still matters, especially for questions the rules do not address.
Points to negotiate
- Amount, and any reduction as performance progresses
- Expiry date or event, and what happens if the underlying contract is extended
- Whether a demand must be accompanied by a statement of breach or other documents
- Whether partial or multiple demands are allowed
- Governing rules, law and jurisdiction
- Counter-guarantee arrangements if a local bank must issue the guarantee
Extend or pay
Beneficiaries sometimes make a demand in the alternative: extend the guarantee or pay. Applicants should anticipate this as expiry approaches and agree a strategy with their bank and advisers in advance.
Abusive calls
Courts in many jurisdictions will restrain payment under a demand guarantee only in narrow circumstances, often involving clear fraud. The threshold is high and varies by jurisdiction. An applicant facing a demand it considers unjustified should contact counsel immediately.
Illustrative scenario (hypothetical)
A contractor supplying water-treatment equipment provides a 10% performance guarantee subject to URDG 758, payable on the beneficiary's demand stating that the contractor is in breach. A dispute arises over delayed commissioning, which the contractor blames on the beneficiary's late site readiness. Two weeks before expiry, the beneficiary sends an "extend or pay" demand. The contractor's options are limited: it can agree to extend, negotiate, or try to persuade a court that the demand is fraudulent or abusive, which is a high threshold in most jurisdictions. Had the guarantee wording tied reduction to milestones, and had the contractor tracked expiry and prepared a negotiation strategy in advance, its position would have been stronger.
Frequently confused points
The title "guarantee", "bond" or "standby" does not decide whether an instrument is payable on demand; the wording does. A demand guarantee is generally payable even if the beneficiary's underlying claim is disputed; the applicant's remedy is usually to recover the money later under the contract. Counter-guarantees, used when a local bank issues the guarantee, create a separate chain of undertakings that must be aligned. Expiry by date and expiry by event behave differently, and event-based expiry can create uncertainty.
Questions to ask before agreeing wording
- Is the instrument payable on simple demand or on proof of liability?
- Which rules and law govern it?
- What must a demand contain?
- Does the amount reduce as performance progresses?
- What is the expiry date or event?
- Is a counter-guarantee needed, and do the two instruments match?
- What happens if the contract is extended?
Where advisers fit
Banks issue guarantees and advise on their own requirements; counsel advises on wording, governing law and challenges to demands. MITIGATE PLUS compares wording with the contract, tracks expiry and reduction and documents procedures. It does not issue or procure guarantees or charge fees contingent on finance.
Key terms
- Applicant: the party at whose request the guarantee is issued, usually the supplier or contractor
- Beneficiary: the party entitled to demand payment
- Guarantor: the bank or institution that issues the guarantee
- Counter-guarantee: an undertaking by the applicant's bank to the local guarantor, supporting a local guarantee
- Complying demand: a demand that meets the guarantee's requirements as to form, content and timing
- Expiry: the date or event after which no demand may be made
- Reduction clause: a provision reducing the amount as performance milestones are achieved
A note on tracking
Guarantees are easily forgotten until a demand arrives. A tracker recording each instrument's amount, beneficiary, rules, expiry, reduction events, counter-guarantees and the underlying contract milestones lets a business anticipate extend-or-pay requests, release instruments promptly when obligations are met and reduce bank charges for guarantees no longer needed.
Releasing guarantees
When obligations are fulfilled, ask the beneficiary to return the original or confirm release in writing, and ask the bank to cancel the instrument. Until that happens, the guarantee may remain on the applicant's credit lines and continue to attract fees.
Sources
Primary materials named for reference; their text is not reproduced. Where a free official text exists, the citation links to it. Check whether a source has been amended since this article was last updated. See our editorial policy for how sources are chosen and checked.
- ICC Uniform Rules for Demand Guarantees (URDG 758) — consult the official ICC publication
- International Standby Practices (ISP98)
Related reading
- ArticleLetters of credit: the discrepancies that delay payment4 min read
- Practical guideGuide: a documentary credit workflow from application to payment5 min read
- ChecklistLetter of credit discrepancy checklist1 min read
- ChecklistBank onboarding documents checklist1 min read
- BriefingDocumentary credit and EPC or supply contract disputes1 min read