Remote witnessing
Where travel is impractical, agree a remote-witnessing method in advance: live video of the full test, independent data logging, timestamps and a signed record. Remote witnessing works best when it supplements, rather than replaces, an independent inspector on site.
Why acceptance matters
Acceptance is often the point at which major commercial consequences occur: final payment becomes due, risk or responsibility may pass, warranty periods begin and liquidated damages for delay stop running. If the contract does not define acceptance clearly, these consequences become arguments.
FAT, SAT and performance tests
A factory acceptance test (FAT) takes place at the manufacturer's premises before shipment, so that problems can be fixed where the expertise and tools are. A site acceptance test (SAT) takes place after installation, checking that the equipment works in its real environment and connections. Performance or reliability tests may follow, measuring output, availability or quality over a defined period.
Writing measurable criteria
Good acceptance criteria are specific and measurable. "Operates satisfactorily" invites dispute; "produces at least the stated output per hour at the specified tolerance for a continuous four-hour run using the buyer's materials" does not. Criteria should state the test method, conditions, inputs, measuring equipment, duration and pass or fail thresholds.
Who witnesses and who signs
The contract should say who may attend, how much notice must be given, and who signs the test record. Many buyers appoint an independent inspector or engineer to witness tests. The buyer usually signs any acceptance certificate, often based on the inspector's report. Where tests are witnessed remotely, the method of observation should be agreed in advance.
Failed tests and punch lists
The contract should say what happens if a test is failed: correction and retest, price reduction, or ultimately rejection. Minor defects that do not prevent acceptance are commonly recorded in a punch list with deadlines for completion. Do not authorise shipment or sign acceptance while material items remain open unless the commercial consequences are understood.
Checklist before the test
- Agreed written protocol and criteria
- Calibrated measuring equipment
- Inputs and materials available
- Witnesses appointed and notified
- Record and signature process agreed
Illustrative scenario (hypothetical)
A food processor buys a packaging line with a performance guarantee of a stated number of packs per minute. The contract refers to a "performance test to be agreed". At installation, the supplier proposes a 30-minute test using its own film; the buyer wants an eight-hour test using its production film and products. Neither will sign. Payment of the final instalment and the start of the warranty period both depend on acceptance, so the line sits idle while the parties argue. A protocol agreed at contract stage — inputs, duration, measurement and tolerance — would have turned a dispute into a routine test.
Frequently confused points
Passing a FAT does not mean the equipment will pass on site, because site conditions, utilities and interfaces differ. Signing a delivery note is not acceptance unless the contract says so. Taking equipment into commercial use can, under some contracts or laws, amount to deemed acceptance; the contract should say whether it does. Liquidated damages for performance shortfall are different from damages for delay.
Questions to ask when drafting the protocol
- What exactly is measured, and with what equipment?
- What inputs and materials are used, and who supplies them?
- How long does the test run, and under what conditions?
- What tolerance applies?
- Who witnesses, and who signs?
- What happens if the test fails, and how many retests are allowed?
- When, if ever, is acceptance deemed?
Where advisers fit
Independent inspectors and engineers witness tests and give technical views; counsel advises on acceptance and remedies. MITIGATE PLUS schedules tests, prepares protocol checklists from the contract, reviews reports and tracks punch lists. It does not certify equipment or sign acceptance on a client's behalf.
Key terms
- Factory acceptance test (FAT): testing at the manufacturer's site before shipment
- Site acceptance test (SAT): testing after installation at the buyer's site
- Performance test: measurement of output, availability or quality against guaranteed values over a defined period
- Punch list: a list of minor defects or incomplete items to be closed by agreed dates
- Deemed acceptance: acceptance treated as having occurred because of an event, such as commercial use or expiry of a period, if the contract provides for it
- Witness point: a stage at which the buyer or its inspector is entitled to attend
- Hold point: a stage beyond which work may not proceed until the buyer or inspector releases it
A note on documentation
Acceptance generates important documents: test protocols, raw data, calibration certificates for measuring equipment, signed test records, punch lists and acceptance certificates. Keep them together and retain them for the warranty period and beyond. If a performance dispute arises later, these records are usually the first evidence counsel and engineers will ask for.
Planning the test calendar
Book inspectors and witnesses early, allow time for retests, and align the FAT date with shipping schedules and any letter of credit shipment date. Compressed test windows are a common reason for incomplete tests and later disputes.
Sources
Primary materials named for reference; their text is not reproduced. Where a free official text exists, the citation links to it. Check whether a source has been amended since this article was last updated. See our editorial policy for how sources are chosen and checked.
- The procurement contract and its technical schedules
