How to use this guide
This guide walks through an international sale or supply agreement in the order the commercial team usually needs to think about it: who the parties are, what is being bought, how it moves, how it is paid for, what happens when things go wrong, and how the relationship ends. At each stage it identifies the questions to answer and the documents to hold. It does not replace advice from counsel qualified in the governing law, who should review the final text.
Stage 1 — the parties
Start by confirming exactly who is contracting. Use full legal names and registration numbers taken from the official registry, not from letterheads. If the counterparty is part of a group, decide which entity should contract and whether a parent guarantee is needed. Check signatory authority: in some jurisdictions only certain officers may bind a company, and powers of attorney may need notarisation or legalisation. Complete counterparty screening, including beneficial ownership and sanctions, and record the result before negotiations go far.
Stage 2 — the subject matter
Attach or reference a precise specification. Many disputes arise because the specification was a quotation, an email or a sample whose status was never fixed. Record the version that applies and how changes are agreed. For goods with quality tolerances, state the tolerance, the method of measurement and who measures. For services or installation, define deliverables and acceptance.
Stage 3 — delivery and risk
Choose the Incoterms rule that matches how the goods will actually move, and state the named place precisely and the edition. Set out the delivery period and how it is measured, notice requirements before delivery (for example, readiness notices or nominations), and what documents must accompany delivery. Address title separately: when it passes, whether it is retained until payment, and how retention will operate in the countries involved. Make sure insurance matches the rule chosen and the buyer's and any lender's requirements.
Stage 4 — price and payment
State the price, currency and what it includes — taxes, duties, packaging, freight. If prices can change, set out the mechanism: indexation, fixed review dates or open-book review, and what data supports it. Choose a payment method that fits the risk: open account, documentary collection, documentary credit, advance payment against a guarantee, or a combination. List the documents required for payment and check that they are obtainable. Add late-payment provisions where the governing law allows them.
Stage 5 — inspection and acceptance
Say who inspects, where, when and to what standard; whether the buyer may attend or appoint its own inspector; which certificate is final; and how disputes over inspection results are resolved. For equipment, define factory and site acceptance tests with measurable criteria.
Stage 6 — remedies
Decide what happens if goods are late, defective or short: repair, replacement, price reduction, liquidated damages, termination. Review liability caps and exclusions carefully with counsel; they often determine the real allocation of risk. Check how warranties interact with statutory implied terms under the governing law, and whether the UN Sales Convention applies.
Stage 7 — events beyond control
Review force majeure, hardship and change-in-law provisions against realistic risks in the trade lane: export bans, sanctions, port closures, epidemics. Note the notice requirements and evidence the clause demands.
Stage 8 — confidentiality, IP and data
Address confidentiality, ownership of designs and tooling, licences to use software and the handling of any personal data exchanged.
Stage 9 — notices, law and disputes
Record notice addresses and methods and put them in a register. Confirm governing law and forum with counsel. Consider whether a tiered clause — negotiation, mediation, then arbitration — fits the relationship, and whether an arbitral award would be enforceable where the counterparty's assets are.
Stage 10 — duration and exit
Set the term, renewal mechanism and termination rights, and what happens to open orders, stock, guarantees and data on exit.
Documents to keep on file
- Signed contract with all schedules and the final specification
- Registry extracts and authority evidence for signatories
- Screening record
- Negotiation issues list showing how positions were resolved
- Notice and deadline register
- Insurance and payment instruments
Illustrative scenario (hypothetical)
A UK manufacturer agrees to supply control panels to a buyer in South-East Asia. The buyer's purchase order refers to its general terms; the manufacturer's quotation refers to its own. Price and quantity are agreed by email; the specification is a drawing revised twice since quotation. Using this checklist, the manufacturer's team identifies five issues before signature: competing standard terms, an unstated Incoterms edition, a specification revision not referenced in the order, a letter of credit requiring a certificate the manufacturer cannot obtain, and a notice clause pointing to an address the buyer no longer uses. Each is resolved in a short side letter reviewed by counsel. None would have been expensive to fix before signature; each could have been expensive afterwards.
Roles and responsibilities
- The commercial team owns the term sheet, issues list and checklist
- Technical staff confirm the specification and acceptance criteria
- Finance confirms payment terms, security and documents
- Logistics confirms delivery terms and documents
- Counsel qualified in the governing law reviews and settles the legal text
- An authorised signatory signs only once the checklist is complete
Frequently asked questions
Should we always use our own terms? Using your own terms gives you a familiar starting point, but a counterparty with bargaining power will often insist on its own. What matters is that the critical points are negotiated and that conflicts between documents are resolved expressly.
Do we need a long contract for a one-off sale? Not necessarily. A short contract that clearly covers parties, goods, delivery, payment, inspection, remedies, law and disputes is often better than a long template that nobody reads.
How often should a framework contract be reviewed? At least at each renewal, and whenever trade lanes, products or regulation change significantly.
Limitations
This checklist supports commercial preparation. It is not legal advice; have the final text reviewed by independent counsel qualified in the governing law.
Sources
Primary materials named for reference; their text is not reproduced. Where a free official text exists, the citation links to it. Check whether a source has been amended since this article was last updated. See our editorial policy for how sources are chosen and checked.
- United Nations Convention on Contracts for the International Sale of Goods (CISG), 1980 (official text, opens in a new tab)
- ICC Incoterms® 2020 — consult the official ICC publication
Related reading
- ArticleIncoterms and the moment risk really transfers4 min read
- ArticleNotice clauses and time bars: the quiet contract killers4 min read
- ChecklistCommercial contract pre-signature checklist2 min read
- BriefingCross-border contract negotiation and documentation1 min read
- BriefingGoverning law, jurisdiction and arbitration clauses1 min read
- BriefingForce majeure, hardship and change in law in practice1 min read