Before you start
Identify, for each fixture, who is responsible for collecting port documents during the voyage and who prepares the claim afterwards. Agree a standard folder structure for each voyage and port so that documents are filed as they arrive. Check, at fixture stage, whether the charterparty's time-bar clause lists the documents that must accompany a claim, and share that list with the master and agents so they know which documents must be signed and returned.
Who this guide is for
Owners, operators, charterers and traders who need to submit or respond to a demurrage claim. It describes how to assemble a claim pack that complies with typical charterparty time-bar clauses and can be checked quickly by the other side. It does not replace advice from maritime counsel on construction of the charterparty.
Step 1 — identify the time bar
Read the charterparty for a demurrage time-bar clause. Note the period, the event from which it runs (often completion of discharge) and, crucially, which documents must accompany the claim. Some clauses bar claims submitted without the specified supporting documents. Diarise the deadline immediately.
Step 2 — collect the documents
Typical documents include:
- The charterparty and fixture recap, with riders and addenda
- Voyage orders and any variations
- Notices of readiness, with evidence of tender time and method
- Statements of facts for each port, signed by master and agents
- Pumping logs and hose connection and disconnection records, for liquid cargo
- Weather records, where weather exceptions are claimed
- Port logs, berth and anchorage records
- Correspondence about delays or shifting
Step 3 — reconcile the times
Compare times across the NOR, statements of facts and logs. Where they differ, identify which document the charterparty treats as decisive and note the discrepancy rather than ignoring it.
Step 4 — calculate
Prepare a laytime statement showing laytime allowed, when it started, each exception or interruption claimed with its clause reference and evidence, time used and time on demurrage. Apply the demurrage rate and any pro-rating for shared berths or multiple parcels. Show every calculation step.
Step 5 — prepare the cover letter
Summarise the claim, the amount and the basis, and list every enclosed document. Address it to the party and address the charterparty specifies.
Step 6 — submit and record
Submit within the time bar, by the method required, and keep proof of submission. Record acknowledgement.
Step 7 — respond to queries
Answer the other side's queries promptly and with documents. If agreement cannot be reached, refer to maritime counsel well before any arbitration time limit.
Responding to a claim
If you receive a claim, check it against the charterparty: was the NOR valid, were exceptions correctly applied, are the times supported, were the required documents enclosed in time? Prepare an alternative laytime statement where appropriate.
Pitfalls to avoid
- Submitting without documents the time-bar clause requires
- Unsigned or inconsistent statements of facts
- Calculations without clause references
- Sending the claim to the wrong party
- Ignoring back-to-back sale contract laytime terms
Illustrative scenario (hypothetical)
A chemical tanker discharges at two ports. The owner's operations team, following this guide, diarises the charterparty's 90-day time bar from completion of discharge at the second port. It collects the NORs, statements of facts and pumping logs for both ports and notices that the pumping log at the second port shows a period of reduced rate attributed by the terminal to shore restrictions. The laytime statement treats that period according to the charter's pumping clause, with the supporting terminal letter. The pack is submitted on day 40 with a complete document list. Charterers query two items; both are answered with documents, and the claim is settled without arbitration.
Roles and responsibilities
- Operations collects port documents during the voyage
- The claims team prepares the laytime statement and pack
- Agents provide signed statements of facts
- The master confirms NOR tender and readiness
- Maritime counsel advises on disputed construction points
- MITIGATE PLUS can reconcile documents, prepare calculations and assemble packs
Frequently asked questions
What if a document required by the time-bar clause is unavailable? Submit what you have within time, explain what is missing and why, and take advice; whether the claim survives depends on the clause and its interpretation.
Can demurrage be claimed against a cargo receiver? Usually only if the receiver is party to a contract providing for it, such as a sale contract with laytime terms or bill of lading terms incorporating the charter. Advice is needed.
Is there a limit on demurrage? Demurrage generally runs until cargo operations are complete, unless the charter or law provides otherwise. Very prolonged delay may raise other questions for counsel.
How are shared berths or multiple parcels handled? According to the charter's pro-rating provisions; show the method clearly in the calculation.
Pack checklist
- Time bar and required documents identified
- Charter, recap and voyage orders
- NORs and evidence of tender
- Signed statements of facts for each port
- Pumping and weather records where relevant
- Laytime statement with clause references
- Cover letter with document list and proof of submission
Key terms
- Laytime statement: the calculation of time allowed, time used and demurrage or despatch
- Pumping clause: a provision on minimum discharge rates for liquid cargo and how shortfalls are treated
- Pro-rating: sharing time between parcels or charterers at a common berth
A typical timetable
During the voyage, operations collects NORs, statements of facts and logs as each port call ends. Within a week of completing discharge, the claims team reconciles times and identifies gaps, asking agents for any missing signed documents. Within two to three weeks, a draft laytime statement is reviewed internally against the charter. The pack is then submitted with a full document list, well inside the time bar, leaving room to respond to queries. Waiting until the last days of the period is the most common avoidable risk in demurrage practice, because one missing document can defeat the whole claim.
Responding efficiently to queries
Keep the pack organised by port and document type, so that each query can be answered with a page reference. Track open queries in a log until the claim is agreed.
Limitations
Formal maritime arbitration is conducted by qualified professionals; screening for sanctions is applied to every matter.
Sources
Primary materials named for reference; their text is not reproduced. Where a free official text exists, the citation links to it. Check whether a source has been amended since this article was last updated. See our editorial policy for how sources are chosen and checked.
- BIMCO Laytime Definitions for Charter Parties 2013 — consult the official text where incorporated
- The charterparty and its incorporated clauses
Related reading
- ChecklistCharterparty claim evidence checklist1 min read
- ArticleLaytime and demurrage: reading the statement of facts4 min read
- ArticleThe three functions of a bill of lading4 min read
- ChecklistVessel sale and purchase documents checklist1 min read
- BriefingCharterparty, cargo disputes and ship arrest coordination1 min read
- BriefingVessel sale and purchase: coordinating the MOA process1 min read