Back-to-back exposure
Traders who charter vessels and also sell or buy cargo on laytime terms should compare the charter and sale-contract provisions at fixture stage, so that demurrage paid to owners can be recovered from the cargo counterparty where intended.
The vocabulary
Laytime is the period the charterer is allowed, without paying extra, for loading and discharging. Demurrage is the agreed rate payable to the owner when laytime is exceeded; despatch, where agreed, is paid by the owner when cargo operations finish early. Detention is a claim for damages for delay outside the laytime regime. These concepts are defined by the charterparty and, where incorporated, by standard definitions such as BIMCO's Laytime Definitions for Charter Parties 2013.
When laytime begins
Under most voyage charters, laytime starts after the vessel has arrived at the agreed place, is ready to load or discharge, and has tendered a valid notice of readiness (NOR). Many charters add a notice period after tender before time starts to count. Whether the vessel is an "arrived ship" depends on whether the charter is a berth or a port charter and on clauses such as "whether in berth or not" (WIBON). An NOR tendered before the vessel is truly ready may be invalid, which can delay or prevent laytime starting unless the charterer has waived the defect or another clause applies.
Exceptions and interruptions
Charterparties commonly exclude certain periods from laytime: weekends and holidays, bad weather, shifting between berths, strikes or stoppages beyond the charterer's control, and periods when the vessel is not available because of the owner's fault. The precise wording matters. "Once on demurrage, always on demurrage" is a frequently quoted principle, but its application depends on the charter and governing law.
The evidence
Laytime disputes are decided on documents: the NOR and its tender, the statement of facts signed by master and agents, pumping logs for liquid cargo, weather records, port logs and correspondence. Inconsistent times between these records are the most common source of disagreement.
Time bars
Many charters include a demurrage time-bar clause requiring the claim, with specified supporting documents, to be submitted within a fixed period after discharge. Claims submitted late, or without the documents the clause requires, may be barred. Diarise the period on completion of discharge and assemble the documents immediately.
Practical checks
- Confirm the berth or port nature of the charter and any WIBON or similar clause
- Check the NOR tender method and the vessel's readiness at the time
- Reconcile times between NOR, statement of facts and logs
- List every exception claimed and the evidence for it
- Identify the time bar and required documents
Illustrative scenario (hypothetical)
A vessel arrives at a congested discharge port and anchors outside port limits. The master tenders notice of readiness by email on arrival at the anchorage. The charter is a berth charter with a "whether in port or not" (WIPON) clause, and requires NOR to be tendered within office hours. The NOR was sent at 2200 on a Saturday. Owners claim laytime from the following morning; charterers argue the NOR was invalid because it was tendered outside office hours and that laytime started only when the vessel berthed four days later. The answer depends on the precise wording, any waiver by charterers' conduct and the governing law. A careful reconstruction of times from the NOR, port logs and agents' records is the starting point for either side.
Frequently confused points
Laytime and demurrage belong to voyage charters; time charters work on hire and off-hire instead. "Reversible" laytime allows time saved at one port to be used at another; "average" laytime calculates separately and then offsets. Despatch is not automatic; it must be agreed. Demurrage is liquidated damages for delay in loading or discharging; other losses caused by delay may need a separate claim for detention or damages. Sale contracts often contain their own laytime terms that do not exactly match the charter, creating back-to-back exposure for traders.
Questions to ask on every voyage
- Is the charter a berth or port charter, and does it contain WIBON, WIPON or similar wording?
- When and how must NOR be tendered?
- Which exceptions apply, and what evidence supports each?
- Are statements of facts signed and consistent?
- Is laytime reversible or averaged across ports?
- What does the time-bar clause require, and by when?
- Do the sale contracts mirror the charter terms?
Where advisers fit
Maritime counsel advises on construction and represents parties in arbitration; shipbrokers and operators provide market and operational input. MITIGATE PLUS reconciles documents, prepares laytime statements and assembles claim packs within time bars. It does not give legal opinions or imply any professional membership.
Key terms
- Notice of readiness (NOR): the master's notice that the vessel has arrived and is ready to load or discharge
- Statement of facts (SOF): the record of times and events at a port
- Berth charter: a charter under which the vessel must reach the berth to arrive
- Port charter: a charter under which arrival within the port suffices
- Demurrage time bar: a clause requiring claims and documents within a fixed period
Sources
Primary materials named for reference; their text is not reproduced. Where a free official text exists, the citation links to it. Check whether a source has been amended since this article was last updated. See our editorial policy for how sources are chosen and checked.
- BIMCO Laytime Definitions for Charter Parties 2013 — consult the official text where incorporated
- The charterparty, its riders and incorporated clauses
Related reading
- Practical guideGuide: assembling a laytime and demurrage claim pack5 min read
- ArticleThe three functions of a bill of lading4 min read
- ChecklistVessel sale and purchase documents checklist1 min read
- ChecklistCharterparty claim evidence checklist1 min read
- BriefingCharterparty, cargo disputes and ship arrest coordination1 min read
- BriefingVessel sale and purchase: coordinating the MOA process1 min read